Contractor sets new date for Ofankor-Nsawam road completion

Article arrow_drop_down

Work on the Ofankor-Nsawam Dual Carriage Road project, which has already missed the initial July 20, 2024, completion date, will miss the revised completion date of May 21, 2025. 

The completion of the project will be delayed by 15 more months because of unresolved compensation issues for persons affected by the project and the relocation of service lines of utility agencies such as the Electricity Company of Ghana and Ghana Water Limited.

Per the current progress report, the project is 74 per cent complete, and thus, cannot be delivered on the revised completion date of May 21, this year.

The Chief Resident Engineer of the project, Kwabena Bempong, explained that out of 328 structures that were on the project’s right of way, 76 of the owners of those facilities qualified for compensation out of which 40 of them received some compensation.

He said the contractor’s quest to speed up work on the project hit a snag after some of the affected persons took the case to court for redress.

Again, he said since November last year, the contractor had not been able to do any meaningful work because of financial challenges related to compensation payment.

Select Committee

This came to light when the Parliamentary Select Committee on Roads and Transport paid a working visit to the project site last Friday.

The committee was led by its Chairman and Member of Parliament (MP) for Wassa East, Isaac Adjei Mensah, and the Ranking Member, Kennedy Osei Nyarko.

The committee also visited the Obetsebi Lamptey Interchange and the Winneba-Kasoa Road Expansion projects to ascertain the progress of work and the challenges that needed to be addressed.

Obetsebi Interchange

At the Obetsebi Interchange project, it came to light that outstanding works on the €87-million facility were progressing at a snail’s pace because of funding challenges resulting from interim payment certificates (IPCs) that have not been fully honoured by the government.

Although the work on the second phase of the project had exceeded the 96 per cent completion point, the Resident Engineer of Fas Consult, Owusu Sekyere Antwi, said delays in honouring the outstanding IPC of about €20 million had made it difficult for the contractors – QG Construction Limited, to complete the work at the end of the first quarter of this year as envisaged.

Mr Antwi said part of the IPCs were paid last year but a chunk of it was yet to be honoured.

In January this year, Mr Antwi had told the Daily Graphic that final ancillary works were ongoing on portions of the facility to enable the contractors to hand over the €87-million project by the end of March, this year.

He had also indicated that the outstanding works included the laying of pavement blocks on the walkways, doing the wearing course (second course of asphalt), road lines and markings, road furniture (road signs, directional signs) and the installation of traffic lights.

Kasoa-Winneba Road Project

When the committee got to the Kasoa-Winneba project, construction work was progressing steadily.

The Resident Engineer of ABP Consult said the combined physical work for Lot A of the project, which comprised the construction of interchanges at Sapato, Buduburam, Bereku, Akoti, and two footbridges, was 47 per cent complete.

He said, all things being equal, it was expected that the project would be handed over by the end of March 2027.

General satisfaction

Touching on the Obetsebi Interchange project, Mr Mensah said there was a need to expedite action on the financial regularisation to ensure that work was completed on time.

The Wassa MP urged the contractor to link up with the Ministry of Works and Housing and the Greater Accra Resilient and Integrated Development (GARID) project to complete the drainage infrastructure within the project area.

On the Kasoa-Winneba road project, he said it was refreshing that despite the initial setbacks, the project was progressing steadily.

Mr Mensah also said since the government did not owe the contractors, they must work around the clock to finish the project.

Touching on the issue of compensation payments, he stressed that there was a need for all stakeholders to join hands and resolve all the thorny issues to allow for the smooth execution of the Ofankor-Nsawan and other road projects.

Swift action

The Ranking Member on the committee, Kennedy Osei Nyarko, said the work done by the contractors was generally satisfactory and needed to be sustained and completed.

However, he expressed concern about the protracted shifts in the completion dates of the Ofankor-Nsawam dualisation project.

“This is a 33.4-kilometre road project that was supposed to be completed within 24 months, but it has elapsed for almost a year now and we are made to understand that as long as it keeps delaying, it is costing the government and the taxpayer more money.

“If we are not able to resolve the outstanding issues for the contractor to be able to complete the project, we will end up paying almost double the initial project cost,” he said.

He emphasised the need to swiftly deal with the issues of encroachment and compensation for the project to rebound.

About the author

About the author

Ahmad

More posts Follow

trending_flat
Ada East Assembly fails to confirm President’s DCE nominee

The Ada East Municipal Assembly in the Greater Accra Region on Thursday, May 8, 2025, failed to confirm Kenneth Kabu Kanor, the President’s nominee for the position of District Chief Executive (DCE).Mr Kanor polled 24 votes out of 38 valid votes cast, representing 63.2 per cent, in a process that extended into the night. One vote was rejected, while 13 members voted against him. The nominee required 26 votes to meet the two-thirds threshold necessary for confirmation.By law, the assembly members are expected to reconvene within ten days for a second round of voting to either confirm or reject the nominee. The Greater Accra Regional Minister, Linda Akweley Ocloo, who expressed concern over the outcome, cautioned that Municipal and District Assemblies in the region risk losing out on development opportunities if they fail to confirm the President's nominee. She noted […]

trending_flat
Pope Leo XIV Inaugural Address: ‘May Peace Be With You

Pope Leo XIV was elected on May 8, 2025, becoming the 267th pope and the first ever from the United States in Catholic history. The conclave, which convened 133 cardinal electors in the Sistine Chapel, reached consensus swiftly, with white smoke signaling his election on the second day of voting. Cardinal Prevost’s Background Born in Chicago and of Italian, French, and Spanish descent, Robert Prevost spent decades as an Augustinian missionary in Peru, later overseeing the Vatican’s office for episcopal appointments and earning a reputation as a skilled diplomat within the Curia. Elevated to cardinal by Pope Francis in January 2025, his moderate yet compassionate approach positioned him as a compromise candidate able to bridge progressive and conservative factions. Highlights of the First Speech Greeting of Peace Upon emerging in white on the central balcony, Pope Leo XIV began simply, “Peace be with you,” echoing […]

trending_flat
White Smoke Signals Election of New Pope on Second Day of Conclave

On May 8, 2025, at approximately 6:07 p.m. CEST, white smoke billowed from the chimney of the Sistine Chapel, signaling the successful election of the 267th pope by the College of Cardinals. This historic moment occurred on the second day of the conclave, following four rounds of voting, and was met with jubilant cheers from thousands gathered in St. Peter's Square The conclave was convened after the passing of Pope Francis on April 21, 2025, at the age of 88. A total of 133 cardinal electors participated in the secretive voting process, requiring a two-thirds majority—at least 89 votes—to elect the new pontiff . As per tradition, the identity of the newly elected pope will be announced shortly from the balcony of St. Peter's Basilica with the Latin proclamation "Habemus Papam" ("We have a pope"). The new pope will then […]

trending_flat
Mahama’s Government Shows Promise but Faces Looming Challenges – Experts

President John Dramani Mahama's return to Ghana's highest office has been met with both optimism and caution. While his administration has initiated several reforms and fulfilled a significant portion of its early promises, experts highlight persistent challenges that could impede sustained progress. In his first 120 days, President Mahama claims to have fulfilled 72% of his pledges, including the launch of a code of conduct for government officials and the initiation of investigations into unresolved murders and financial scandals . These actions underscore a commitment to transparency and accountability. However, analysts point out that some of these achievements may be overstated, noting that systemic issues like corruption and bureaucratic inertia remain deeply entrenched . The administration's economic reforms, while ambitious, are still in their infancy and face execution challenges, particularly in creating sustainable job opportunities . Furthermore, Ghana's economy, though […]

trending_flat
Kwakye Ofosu: Presidency Restructuring Saves Ghana Over GH₵400 Million

In a recent statement, Felix Kwakye Ofosu, Ghana's Minister of State in charge of Government Communications, announced that the government's restructuring of the presidency has resulted in savings exceeding GH₵400 million. This initiative is part of a broader effort to enhance fiscal responsibility and streamline government operations. A significant aspect of this restructuring involved reducing the number of personnel managing the President's communications. Previously, 28 individuals were assigned to this task; the number has now been reduced to 7, leading to substantial cost savings. Kwakye Ofosu emphasized that these measures reflect the government's commitment to doing more with fewer resources, ensuring that public funds are utilized efficiently. He also addressed and refuted claims that his office had been allocated GH₵78 million, clarifying that the mentioned funds were designated for operational budgets of agencies such as the Ghana Broadcasting Corporation (GBC), […]

trending_flat
Dr. Paa Kwesi Baidoo Assumes Role as KATH CEO with Commitment to Transparent Leadership

Dr. Paa Kwesi Baidoo has officially taken over as the Acting Chief Executive Officer (CEO) of the Komfo Anokye Teaching Hospital (KATH), pledging to lead with a "clean heart and clear mind" and to prioritize the hospital's mission over personal interests. In his inaugural address to the management team on May 7, 2025, Dr. Baidoo emphasized his dedication to enhancing the hospital's capacity to meet patient expectations and to fostering a collaborative work environment. Dr. Baidoo, a Consultant Orthopaedic Surgeon and Fellow of both the West African College of Surgeons and the Ghana College of Physicians and Surgeons, previously headed KATH's Trauma and Orthopaedics Directorate and served as Chairman of the Ashanti Regional division of the Ghana Medical Association. He succeeds Prof. Otchere Addai-Mensah, whose tenure from December 2022 to April 2025 was marked by significant advancements, including the expansion […]

Related

trending_flat
Amérique au Vatican : Robert Prevost devient Léon XIV, premier pape américain

Le cardinal Robert Prevost, 69 ans, originaire de Chicago, a été élu pape ce jeudi, devenant ainsi le premier Américain à accéder au trône de Saint Pierre. Il succède à François et a choisi le nom de Léon XIV. Membre de l’ordre des Augustins, Prevost a passé une grande partie de sa vie missionnaire au Pérou, où il a exercé les fonctions d’évêque de Chiclayo entre 2015 et 2023. Figure discrète dans les médias, il s’est forgé une réputation de pasteur proche des pauvres et des migrants, en particulier ceux du Venezuela. Dernièrement à la tête du dicastère pour les évêques, il était chargé de la nomination des prélats dans le monde entier. Son élection s’inscrit dans la continuité sociale et pastorale du pontificat de François, avec un message fort : « Notre mission est d’agrandir la tente et de […]

trending_flat
Ada East Assembly fails to confirm President’s DCE nominee

The Ada East Municipal Assembly in the Greater Accra Region on Thursday, May 8, 2025, failed to confirm Kenneth Kabu Kanor, the President’s nominee for the position of District Chief Executive (DCE).Mr Kanor polled 24 votes out of 38 valid votes cast, representing 63.2 per cent, in a process that extended into the night. One vote was rejected, while 13 members voted against him. The nominee required 26 votes to meet the two-thirds threshold necessary for confirmation.By law, the assembly members are expected to reconvene within ten days for a second round of voting to either confirm or reject the nominee. The Greater Accra Regional Minister, Linda Akweley Ocloo, who expressed concern over the outcome, cautioned that Municipal and District Assemblies in the region risk losing out on development opportunities if they fail to confirm the President's nominee. She noted […]

trending_flat
Pope Leo XIV Inaugural Address: ‘May Peace Be With You

Pope Leo XIV was elected on May 8, 2025, becoming the 267th pope and the first ever from the United States in Catholic history. The conclave, which convened 133 cardinal electors in the Sistine Chapel, reached consensus swiftly, with white smoke signaling his election on the second day of voting. Cardinal Prevost’s Background Born in Chicago and of Italian, French, and Spanish descent, Robert Prevost spent decades as an Augustinian missionary in Peru, later overseeing the Vatican’s office for episcopal appointments and earning a reputation as a skilled diplomat within the Curia. Elevated to cardinal by Pope Francis in January 2025, his moderate yet compassionate approach positioned him as a compromise candidate able to bridge progressive and conservative factions. Highlights of the First Speech Greeting of Peace Upon emerging in white on the central balcony, Pope Leo XIV began simply, “Peace be with you,” echoing […]

trending_flat
White Smoke Signals Election of New Pope on Second Day of Conclave

On May 8, 2025, at approximately 6:07 p.m. CEST, white smoke billowed from the chimney of the Sistine Chapel, signaling the successful election of the 267th pope by the College of Cardinals. This historic moment occurred on the second day of the conclave, following four rounds of voting, and was met with jubilant cheers from thousands gathered in St. Peter's Square The conclave was convened after the passing of Pope Francis on April 21, 2025, at the age of 88. A total of 133 cardinal electors participated in the secretive voting process, requiring a two-thirds majority—at least 89 votes—to elect the new pontiff . As per tradition, the identity of the newly elected pope will be announced shortly from the balcony of St. Peter's Basilica with the Latin proclamation "Habemus Papam" ("We have a pope"). The new pope will then […]

trending_flat
Mahama’s Government Shows Promise but Faces Looming Challenges – Experts

President John Dramani Mahama's return to Ghana's highest office has been met with both optimism and caution. While his administration has initiated several reforms and fulfilled a significant portion of its early promises, experts highlight persistent challenges that could impede sustained progress. In his first 120 days, President Mahama claims to have fulfilled 72% of his pledges, including the launch of a code of conduct for government officials and the initiation of investigations into unresolved murders and financial scandals . These actions underscore a commitment to transparency and accountability. However, analysts point out that some of these achievements may be overstated, noting that systemic issues like corruption and bureaucratic inertia remain deeply entrenched . The administration's economic reforms, while ambitious, are still in their infancy and face execution challenges, particularly in creating sustainable job opportunities . Furthermore, Ghana's economy, though […]

trending_flat
Kwakye Ofosu: Presidency Restructuring Saves Ghana Over GH₵400 Million

In a recent statement, Felix Kwakye Ofosu, Ghana's Minister of State in charge of Government Communications, announced that the government's restructuring of the presidency has resulted in savings exceeding GH₵400 million. This initiative is part of a broader effort to enhance fiscal responsibility and streamline government operations. A significant aspect of this restructuring involved reducing the number of personnel managing the President's communications. Previously, 28 individuals were assigned to this task; the number has now been reduced to 7, leading to substantial cost savings. Kwakye Ofosu emphasized that these measures reflect the government's commitment to doing more with fewer resources, ensuring that public funds are utilized efficiently. He also addressed and refuted claims that his office had been allocated GH₵78 million, clarifying that the mentioned funds were designated for operational budgets of agencies such as the Ghana Broadcasting Corporation (GBC), […]

Be the first to leave a comment

Leave a comment

Your email address will not be published. Required fields are marked *

Login to enjoy full advantages

Please login or subscribe to continue.

Go Premium!

Enjoy the full advantage of the premium access.

Stop following

Unfollow Cancel

Cancel subscription

Are you sure you want to cancel your subscription? You will lose your Premium access and stored playlists.

Go back Confirm cancellation